58th Street Greenway Opens

  • Previous
  • Next

The 58th Street Greenway had its official ribbon cutting on Saturday, June 8th. The Philadelphia Inquirer and PlanPhilly were on hand to cover the event, which was commemorated by Deputy Mayor Rina Cutler, Senator Anthony Williams, Councilman Kenyatta Johnson, and Councilman Jannie Blackwell.

PlanPhilly's Christine Fisher explained the trail's significance

After more than three years of planning, more than a year of construction and ongoing community involvement, the 58th Street Greenway opened Saturday. The 1.5 mile, $3.5 million trail provides a critical link between the Cobbs Creek Trail, Bartram's Garden and the trails beyond. As community and project leaders stressed though, the trail is more than a connection. It is a vote of confidence in the South West Philadelphia, Kingsessing neighborhood.

The Inquirer's coverage is here. You can see more photos of the ribbon cutting at the Bicycle Coalition of Greater Philadelphia's Facebook page.


News Roundup: Trails Funded and Trails Cleaned

The Circuit in the news recently:


Trail News Wrap Up: 2012 Ribbon Cuttings and Groundbreakings

  • Previous
  • Next

There are a number of trails under construction that are going to make an appearance soon.

Trails getting ready for ribbon cuttings in 2012

Connector Bridge -- The installation of railings on the prefabricated truss bridge and approach ramps is underway on the Schuylkill River Parks Connector Bridge project over the CSX tracks between Spruce and Locust Streets.  Work continues on the restoration of the Schuylkill River Park and Schuylkill Banks. The City hopes to have an opening ceremony in October, possibly in conjunction with Schuylkill River Park's Fall Festival. Some delays in the procurement of light fixtures may impact a complete opening of the bridge on that day. SRDC will have more information about the opening ceremony in its August newsletter.

Shawmont to Port Royal Avenue -- Construction of the portion of trail from Port Royal Avenue to Montgomery County line is complete. Work continues on the section from Shawmont to Port Royal along Nixon Street, including paving and completion of a retaining wall along the trail parallel to Nixon Street. Work is expected to be completed in Fall 2012. 

Walnut Street Bridge Gateway - The Walnut Street Bridge project is moving along smoothly. Decorative granite pavers were installed on the south sidewalk and the new pedestrian lights have been erected. Some of the “expressway-like” overhead signs have been replaced with smaller signs that are more in keeping with the scale of the bridge, and the rest will be replaced soon. The south sidewalk is finished, so the contractor has switched traffic patterns and is doing similar work on north sidewalk. When this project is completed in September, vehicles, bicyclists and pedestrians should all enjoy a safer, and cheerier, crossing of the river.

Cynwyd Station & Cynwyd Trailhead -- Two projects are nearing completion and there is an October 28th date set for a ribbon cutting for both.  

58th Street Greenway -- The trail is being paved this summer. Trees, lighting, and pedestrian signage will be installed early this fall and a ribbon cutting to follow. Programming to celebrate the greenway is already underway through the Get Active 58th! program. 

Camden Greenway -- Three projects are under construction that will significantly enhance the Camden Greenway: Pearl Street (next to the Ben Franklin Bridge), MLK Boulevard Waterfront Connection, and Pine Street Connector

Tacony Creek - Trail construction of Phase 1 (I & Ramona to Whitaker Avenue) is underway as of July 2012. 

Trails expected to break ground in 2012

Schuylkill Banks Boardwalk

Port Richmond Section of the East Coast Greenway

Penn Street Trail

Realignment of the Delaware Riverfront Trail between Pier 70 and Washington Avenue