Back to Back Trail TIGER Projects in the Spotlight

Two TIGER projects are in the spotlight over the next few days.

The Connector Bridge dedication ceremony is scheduled for 1:00 pm on Saturday, October 20th (rain or shine).  The bridge promises to be a fantastic new access point to the Schuylkill River Trail and is the culmination of an eight year campaign to ensure at-grade and above-grade access to the Trail and Schuylkill Banks. 

The 1:00 pm ceremony will be on the City side of the Bridge, at Schuylkill River Park (25th and Spruce Streets).  Come early for the Fall Festivalthat starts at 11:00 am.  If you want to be among the first to use the Bridge, come run (or volunteer) at the 8:00 am 5K Runnin on the River that is happening that morning. You can register online!

The Port Richmond Trail gets an official groundbreaking on Monday, October 22nd at 10am.  (Note the date change!) Sponsored by the Delaware River City Corporation, this trail is the only TIGER project that is on the Delaware River.  The speakers will make their remarks from within Pulaski Park, Delaware & Allegheny Avenues, and the shovel display for photo opportunities will be on Delaware Avenue, just north of the entrance to the park. 


October Brings Trail Ribbon Cuttings & Groundbreaking

October 19th - Port Richmond Trail

The only trail segment of the East Coast Greenway that received TIGER funds will break ground  on October 19th at 10am.     The event will be held at the intersection of Delaware & Allegheny Avenues, just north of the entrance to Pulaski Park.  The Delaware River City Corporation is the sponsoring organization, along with Philadephia's Parks and Recreation.

October 20th - Connector Bridge

Another trail segment that received TIGER funding is the Connector Bridge, which will provide a above grade crossing between Schuylkill Banks and Schuylkill River Park.  This long anticipated bridge, which the City of Philadelphia built to complement the two at-grade crossings that opened earlier this year, will get a big ribbon cutting on Saturday afternoon at 1pm.  Philadelphia Park and Recreation and Schuylkill River Development Corporation are the sponsoring organizations.  Concurrently, the Friends of Schuylkill River Park is holding its Fall Festival from 10-3pm and the Schuylkill River Park Alliance is holding its 5K Runnin on the River Race at 8am.  

October 28th - Cynwyd TrailHead and Station Rehab Ribbon Cutting – Cynwyd, Lower Merion Twp, PA –  Lower Merion Twp Planning Commission. 12 Noon.  This event is being held in conjunction with the Friends of Cynwyd Trail Fall Festival and will comprise a ribbon cuttinf ro the $625,000 Cynwyd Station Trailhead and $1M renovation of the Cynwyd Station. 


Trail News Wrap Up: 2012 Ribbon Cuttings and Groundbreakings

  • Previous
  • Next

There are a number of trails under construction that are going to make an appearance soon.

Trails getting ready for ribbon cuttings in 2012

Connector Bridge -- The installation of railings on the prefabricated truss bridge and approach ramps is underway on the Schuylkill River Parks Connector Bridge project over the CSX tracks between Spruce and Locust Streets.  Work continues on the restoration of the Schuylkill River Park and Schuylkill Banks. The City hopes to have an opening ceremony in October, possibly in conjunction with Schuylkill River Park's Fall Festival. Some delays in the procurement of light fixtures may impact a complete opening of the bridge on that day. SRDC will have more information about the opening ceremony in its August newsletter.

Shawmont to Port Royal Avenue -- Construction of the portion of trail from Port Royal Avenue to Montgomery County line is complete. Work continues on the section from Shawmont to Port Royal along Nixon Street, including paving and completion of a retaining wall along the trail parallel to Nixon Street. Work is expected to be completed in Fall 2012. 

Walnut Street Bridge Gateway - The Walnut Street Bridge project is moving along smoothly. Decorative granite pavers were installed on the south sidewalk and the new pedestrian lights have been erected. Some of the “expressway-like” overhead signs have been replaced with smaller signs that are more in keeping with the scale of the bridge, and the rest will be replaced soon. The south sidewalk is finished, so the contractor has switched traffic patterns and is doing similar work on north sidewalk. When this project is completed in September, vehicles, bicyclists and pedestrians should all enjoy a safer, and cheerier, crossing of the river.

Cynwyd Station & Cynwyd Trailhead -- Two projects are nearing completion and there is an October 28th date set for a ribbon cutting for both.  

58th Street Greenway -- The trail is being paved this summer. Trees, lighting, and pedestrian signage will be installed early this fall and a ribbon cutting to follow. Programming to celebrate the greenway is already underway through the Get Active 58th! program. 

Camden Greenway -- Three projects are under construction that will significantly enhance the Camden Greenway: Pearl Street (next to the Ben Franklin Bridge), MLK Boulevard Waterfront Connection, and Pine Street Connector

Tacony Creek - Trail construction of Phase 1 (I & Ramona to Whitaker Avenue) is underway as of July 2012. 

Trails expected to break ground in 2012

Schuylkill Banks Boardwalk

Port Richmond Section of the East Coast Greenway

Penn Street Trail

Realignment of the Delaware Riverfront Trail between Pier 70 and Washington Avenue


Camden Quietly Unleashes Its TIGER

There was no golden shovel groundbreaking but a sign on Pearl Street and a few holes in the ground next to the Ben Franklin Bridge in Camden indicates that another TIGER project is underway.


On Pearl St next to the Ben Franklin Bridge
The 5.6 Million dollar project will include bikeway markings (bike lanes or sharrows), sidewalks and lighting on Pearl St, Pine Street and Martin Luther King Boulevard.

Meanwhile an adjacent project on Martin Luther King Blvd includes Camden's first bike lanes. The short two block bike lane is between 7th St and Broadway near Cooper Hospital and the Walter Rand Transportation Center. The TIGER project will build bike lanes from the Camden Waterfront to 5th St, leaving a one block gap between 5th and Broadway.

MLK Blvd at Broadway
Port Richmond Trail Alignment at the Tioga Marine Terminal
In other TIGER news the Port Richmond Trail has been put out for bid with construction slated to begin in late summer or early fall. The project follows Allegheny and Delaware Avenues next to the Tioga Marine Terminal and will be part of the East Coast Greenway. This only leaves the complex Schuylkill Banks Boardwalk project on the drawing board.